Five years and two building contractors, but these houses are still not finished

13 May 2022 By admin

Fort Beaufort resident Fezeka Bawuti doing laundry on the site of her RDP house which was meant to be renovated years ago. Her home has since deteriorated and barely has walls. Photos: Mkhuseli Sizani

  • About 128 families in Fort Beaufort say they were left homeless when contractors abandoned a project to refurbish their homes.
  • The RDP houses were shoddily built by local contractors in the early 2000s.
  • The department of Human Settlements undertook to rebuild and renovate the houses in 2016 but there were setbacks over the years.
  • The last contractor abandoned the refurbishment of the last remaining 128 houses and these families have been living with relatives or in shacks next to their plots ever since.

About 128 families from the Hillside Phase 3 project in Fort Beaufort say they were left homeless when the project to fix their new homes was never completed.

Beneficiaries complained that the houses had no cement foundations, no plaster on the walls, were missing ceilings and had cracks in the walls. The national Department of Human Settlements included these homes in its Rectification Programme with the provincial department as the implementing agency.

Residents say they moved in with relatives or built shacks next to their houses as some homes had to be completely demolished and others needed major repairs. The project initially started in 2016.

The first hiccup came in 2017 when construction workers stopped work over a wage dispute with the contractor. “The contractor said it had no money and the workers looted building material like taps, pipes and baths and washing basins. They also took jojo tanks to pay themselves for the work,” said Zwelakhe Stofile, Ward 20 chairperson of the South African National Civic Organisation (SANCO), explaining how this project had been “overwhelmed by corruption” and maladministration.

A new contractor was appointed to finish the work in 2019. The contractor worked at the site until May 2021 and was to continue until December but abandoned the site. The remaining material was apparently left at the home of the community liaison officer.

Resident Fezeka Bawuti, 60, said her house was built in 2004 and was meant to be renovated. “It had huge cracks from the roof to the floor. It was built with too much sand. On windy days the walls and roof shook. On wet days the walls were wet inside. It had no cement foundation,” she said.

Bawuti said her excitement over the rectification project was short-lived. She had to move back to her parents’ house with her 23-year-old son. “The contractor took our material like zinc, bricks and rafters. Most of my furniture has been damaged. I only come to my RDP site to do my laundry,” she said. Her house currently only has a foundation and half of a wall.

Nomakula Sizani and her six children live in a shack next to her RDP house. They still use the toilet inside the house, though there are no doors.

Nomakula Sizani, 60, lives in a two-room shack with her six children next to her incomplete house. “I feel trapped in this cold shack and I have arthritis. The contractor left my house without a roof, windows and doors. Heavy rains and winds are damaging what was left. We use the toilet inside the unfinished house. Everyone sees us because there are no doors,” she said.

When her house was demolished, Sizani said, she asked relatives to store her furniture, but now they want their space back.

Thandolwethu Kangapi, former community liaison officer for the contractor, told GroundUp that the new contractor had built and renovated 266 houses. He said Human Settlements then extended the contract with an additional 100 houses, in addition to the 28 houses left by the previous contractor. But the new contractor had not done all the work.

Yanga Funani, Eastern Cape Human Settlements spokesperson said the excuse given by the contractor was the impact of Covid-19 on their work. He said the department had not lost any money because the contractors were only paid for each finished unit. “ The remaining budget is R11.8-million to complete the renovations. There was enough money to pay them had they performed and submitted valid claims,” said Funani.

Asked when the project would be completed, Funani only said, “We are in the process of appointing a new contractor.”

© 2022 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

You may republish this article, so long as you credit the authors and GroundUp, and do not change the text. Please include a link back to the original article.

We put an invisible pixel in the article so that we can count traffic to republishers. All analytics tools are solely on our servers. We do not give our logs to any third party. Logs are deleted after two weeks. We do not use any IP address identifying information except to count regional traffic. We are solely interested in counting hits, not tracking users. If you republish, please do not delete the invisible pixel.

Source: GroundUp





Previous: Some NUMSA steel workers to return to work after ArcelorMittal wins interdict
Next: Judge makes landmark ruling on Divorce Act





Filed Under: GroundUp Tagged With: GroundUp

RSS Events

  • Soweto Gets a New Summer Lifestyle Festival as Sugar People & Friends Celebrates Its First Birthday
  • Deftones Setlist: What to Expect From Their 2027 Live Show
  • Hyde Park Corner Brings Out the Stars for This Year’s Spectacular Tree Lighting Celebration!
  • Step Inside: Prudential Center – Home of the New Jersey Devils
  • Exclusive November Imax Lineup Features Iconic Music Legend and a Hollywood Blockbuster
  • Kasi Republic Brings Kwaito, Kasi Cars and Ispantsula Style to Riversands Farm Village This Reconciliation Day
  • Festive Shopping Made Simple at Solly Kramer’s Parkhurst
  • LEDBox Hires Outdoor LED Screen Trailers with On-Site Crew
  • From Busking to the Business of Music: MEX Opens New Doors
  • P!NK Setlist: What to Expect From Her 2027 Live At Sphere Residency

About admin

The one with a "My Complex" - incurable but fun. Grumpy, Cynical, Wise and Idiotic. I can also be found HERE.

Footer

Latest News from Africa

  • Prince Albert – the New King of Jazz
  • Eritrea: Independence Cup in Southern Region
  • President El-Sisi Follows-up on the Evacuation of Egyptian Citizens from Sudan
  • United Arab Emirates welcomes initiation of talks between Sudanese Armed Forces and Rapid Support Forces
  • Ghana’s regions: why creating new territories has caused problems
  • Uganda Red Cross Delivers Relief Aid to Kisoro Floods-Affected Communities
  • President Ramaphosa alarmed over conflict, violence in eastern DRC
  • Mental health: almost half of Johannesburg students in new study screened positive for probable depression
  • Dietary Supplements for Dogs and Cats: Enhancing Well-being
  • Midwives scramble to ensure safe deliveries amid violence in Sudan

RSS MyPR’s Free Press Releases

  • Mphahlele, More crowned 2026 Boxer Super Run Joburg Champions
  • Border Management Conference and Expo 2026 Brings Government, Industry and Regional Partners Together in Pretoria on 18 November
  • Damaged Cars Wanted Pays Gauteng Sellers Before the Tow Truck Leaves
  • RM Capital Explains How It Pays Suppliers Directly to Get Orders Moving
  • Acepak Highlights Tray Forming and Stretch Wrapping for Summer Drinks Runs

© 2026 MyZA · Port Elizabeth, South Africa | Privacy Policy | MyZA content usage