Generation unit breakdowns costing Eskom billions

15 November 2022 By admin

Eskom Chief Operations Officer Jan Oberholzer says the power utility has spent at least R12 billion over the past year on diesel in order to run its open cycle gas turbines (OCGTs).

The OCGTs are the power utility’s emergency generation units which have had to be used extensively during the past year due to the high number of breakdowns at coal fired power stations.

Oberholzer was speaking during Eskom’s State of the System media briefing on Tuesday afternoon.

“In order to supply the demand of the country, we have to run our [OCGTs]…extensively. We have invested in excess of R12 billion this year already burning diesel. Needless to say, Eskom has significant financial challenges as well. If we look at the load shedding that we currently have, it is also to address the scarce financial resources that we have. We do not have money to burn diesel anymore.

“If you look, you’ll find municipalities owing [Eskom] R52 billion but on the other side, we are forced to burn diesel. We are depleting our cash reserves and we are finding ourselves at a very, very delicate position,” he said.

Since January this year, South Africans have endured at least 155 days of load shedding due to some 468 trips at power stations.

Oberholzer said the performance of the generation unit of the power utility – mainly coal fired power stations – has not been good enough.

“There are various reasons for that. But if you look at it, it is not good. This is why we do have load shedding in the country. The number of trips [of generation units] is way too big and this is something that we need to get a handle on.

“Last year when we were talking about the number of trips, we were saying there’s too many trips and this year we’ve actually exceeded that. We really need to get our hands on this unreliability and unpredictability of some of the units at the power stations,” he said.

Oberholzer said as a result of the unpredictability and unreliability of the power system added with major capital projects and repairs and maintenance, “the risk of continued load shedding remains quite high”.

The generation units expected to be taken offline maintenance and repairs include:

  • Koeberg Unit 1 (920MW): To be taken offline on 8 December and expected to return in June 2023
  • Kusile Unit 1 (720MW): Taken offline on October 23 this year with a return date not yet determined.
  • Kusile Unit 2 and 3 (1440MW): On a precautionary outage due to unit 1’s failure. A return to service date has not yet been determined.
  • Medupi Unit 4 (794 MW): Out since August 2021 and is expected to return to service in September 2024.  

“This is the reality of operating a shrunken generation system bereft of any reserve margin – every single breakdown pushes the whole system to the edge.

“This loss of capacity, temporary as it is, will make for a very challenging summer season, particularly as this is our peak planned maintenance period where a number of units at various power stations have to be shut down to conduct much needed maintenance.

“While Eskom works on returning these large units to service, we will have to continue limping along to meet demand for electricity, particularly over the next six to 12 months,” he said.

Acting Managing Director of Generation, Thomas Conradie, outlined some of the power utility’s plans to up the performance of power stations over the next 24 months.

“There’s significant megawatts that we believe we can return from the UCLF [Unplanned Capability Loss Factor] in the order of 3900MW. The Kusile new units…will give us a very healthy 1600MW additional and then also Medupi [unit] 4 which we will bring back in 2024.

“Our expectation is that within the six month period, we will be able to recover 1361MW and a further 1826MW over the next twelve months and 18 months. And after that 1890MW.

“This ultimately brings us up to just over 6000MW that we believe we can receover within the next 24 months,” he said. – SANews.gov.za





Previous: NSFAS investigation recovers R33 million from TVET college
Next: Municipalities advised to impose water restrictions through by-laws





Filed Under: South Africa Tagged With: SAnews

RSS Events

  • Deftones Setlist: What to Expect From Their 2027 Live Show
  • Hyde Park Corner Brings Out the Stars for This Year’s Spectacular Tree Lighting Celebration!
  • Step Inside: Prudential Center – Home of the New Jersey Devils
  • Exclusive November Imax Lineup Features Iconic Music Legend and a Hollywood Blockbuster
  • Kasi Republic Brings Kwaito, Kasi Cars and Ispantsula Style to Riversands Farm Village This Reconciliation Day
  • Festive Shopping Made Simple at Solly Kramer’s Parkhurst
  • LEDBox Hires Outdoor LED Screen Trailers with On-Site Crew
  • From Busking to the Business of Music: MEX Opens New Doors
  • P!NK Setlist: What to Expect From Her 2027 Live At Sphere Residency
  • Dinosaurs Stomp Into Cradlestone Mall This Festive Season

About admin

The one with a "My Complex" - incurable but fun. Grumpy, Cynical, Wise and Idiotic. I can also be found HERE.

Footer

Latest News from Africa

  • Prince Albert – the New King of Jazz
  • Eritrea: Independence Cup in Southern Region
  • President El-Sisi Follows-up on the Evacuation of Egyptian Citizens from Sudan
  • United Arab Emirates welcomes initiation of talks between Sudanese Armed Forces and Rapid Support Forces
  • Ghana’s regions: why creating new territories has caused problems
  • Uganda Red Cross Delivers Relief Aid to Kisoro Floods-Affected Communities
  • President Ramaphosa alarmed over conflict, violence in eastern DRC
  • Mental health: almost half of Johannesburg students in new study screened positive for probable depression
  • Dietary Supplements for Dogs and Cats: Enhancing Well-being
  • Midwives scramble to ensure safe deliveries amid violence in Sudan

RSS MyPR’s Free Press Releases

  • Soweto Gets a New Summer Lifestyle Festival as Sugar People & Friends Celebrates Its First Birthday
  • Renal Supplies Water Systems Plans Dialysis RO Plants From Tap to Drain
  • MoreCut Saws in Alrode Welds Bandsaw Blades to the Length Your Saw Needs
  • When Stretch Fabric Moves in the Press: Pinetown Supplier on Tacky Paper
  • HostEx Cape Sets Out Three Programme Streams for Hospitality Buyers

© 2026 MyZA · Port Elizabeth, South Africa | Privacy Policy | MyZA content usage