Installation of 27 Transformers Starts as at JHNPP Takes Shape

6 September 2021 By admin

Embassy of the United Republic of Tanzania Tel Aviv, Israel

Installation of 27 transformers which will increase transmission voltage of the electricity produced by the turbines from 15 kilovolts to 400 kilovolts at the Julius Nyerere Hydro Electric Power Project (JHNPP) has started. This was revealed by Resident Engineer John Mageni from Tanroads Engineering Consultation Unit (TECU) during a recent official tour of the project's site made by two teams of civil servants.

The team consisted of civil servants from the State House and the Ministry of Public Service Management and Good Governance. Eng. Mageni mentioned other main ongoing work as construction of the power house, which has the length of 305 metres, width of 60 metres and the height of 80 metres.  According to Eng. Mageni, foundation work for the construction of the Switchyard where electricity produced at the JNHPP will be connected to the national grid has already begun.

Other ongoing work include construction of the main dam which has the total length of 1,025 metres at crest level and the height of 131 metres; construction of permanent bridge inside Rufiji River which will have the height of 250 metres and the width of 12 metres; construction of three power water ways with an average of 550 metres length each. The power water ways will channel water to hydro turbines.

He told the two visiting teams that Chinese Company known as Dongfang Electric Corporation is proceeding with the making and installation of nine electromechanical equipment, which will have the capacity to produce 235 Megawatts each. “The work of making and installing these electromechanical equipment, which include hydro-turbines, generators, excitation systems; and Main Inlet Valves has started and is continuing well,” he said.

Expounding, Eng. Mageni said that already six of these electromechanical equipment have arrived at the site whereby two of them have been installed, while others for are in the preparations of being installed. Tanzania Electrical Supply Company (TANESCO) Managing Director, Dr. Tito Mwinuka said the government has paid a total of 2.tri/- to the two Egyptian engineering construction companies — Arab Contractors and Elsewedy Electricity, for the project.

“So far, construction work is going on well and the government has already paid contractors a total of 2,7tri/- out of 6,5tri/-,” Dr. Mwinuka said. Dr. Mwinuka added that supervisory and consultancy work by the government through TANESCO and Tanzania National Roads Agency (TANROADS) is also going on well to make sure that the project is completed on agreed time, which is June, 2022.

Humphrey Donald, a staff from Public Management Service department expressed his appreciation for what he witnessed at the site and congratulated the government for taking step to implement the mega project. Speaking at different times, Permanent Secretary in the Ministry of Public Services Management, Dr. Lauren Ndumbaro and Mr. Nsubili Joshua – Clerk of the Ministers Secretariat Council said the aim of the tour which involved staff of different levels from the two sections was to enable the staff to see in reality, the strategic projects that the government is implementing.

“The aim of this tour is to increase awareness to the civil servants, who have come here today on what their government is doing and motivate them, work even harder as a way of supporting their government and building their country,” they said.

Distributed by APO Group on behalf of Embassy of the United Republic of Tanzania Tel Aviv, Israel.

Media files
Embassy of the United Republic of Tanzania Tel Aviv, Israel
Download logo

Source: Africa Newsroom – APO





Previous: Coronavirus – Malawi: COVID-19 Daily Info Update (06 September 2021)
Next: Statement on Technical Consultative Meeting of the Darfur Permanent Ceasefire Committee





Filed Under: Africa Tagged With: apo

RSS Events

  • Soweto Gets a New Summer Lifestyle Festival as Sugar People & Friends Celebrates Its First Birthday
  • Deftones Setlist: What to Expect From Their 2027 Live Show
  • Hyde Park Corner Brings Out the Stars for This Year’s Spectacular Tree Lighting Celebration!
  • Step Inside: Prudential Center – Home of the New Jersey Devils
  • Exclusive November Imax Lineup Features Iconic Music Legend and a Hollywood Blockbuster
  • Kasi Republic Brings Kwaito, Kasi Cars and Ispantsula Style to Riversands Farm Village This Reconciliation Day
  • Festive Shopping Made Simple at Solly Kramer’s Parkhurst
  • LEDBox Hires Outdoor LED Screen Trailers with On-Site Crew
  • From Busking to the Business of Music: MEX Opens New Doors
  • P!NK Setlist: What to Expect From Her 2027 Live At Sphere Residency

About admin

The one with a "My Complex" - incurable but fun. Grumpy, Cynical, Wise and Idiotic. I can also be found HERE.

Footer

Latest News from Africa

  • Prince Albert – the New King of Jazz
  • Eritrea: Independence Cup in Southern Region
  • President El-Sisi Follows-up on the Evacuation of Egyptian Citizens from Sudan
  • United Arab Emirates welcomes initiation of talks between Sudanese Armed Forces and Rapid Support Forces
  • Ghana’s regions: why creating new territories has caused problems
  • Uganda Red Cross Delivers Relief Aid to Kisoro Floods-Affected Communities
  • President Ramaphosa alarmed over conflict, violence in eastern DRC
  • Mental health: almost half of Johannesburg students in new study screened positive for probable depression
  • Dietary Supplements for Dogs and Cats: Enhancing Well-being
  • Midwives scramble to ensure safe deliveries amid violence in Sudan

RSS MyPR’s Free Press Releases

© 2026 MyZA · Port Elizabeth, South Africa | Privacy Policy | MyZA content usage