Koeberg steam generator replacements hit milestone

22 March 2023 By admin

Eskom has completed a major milestone in the maintenance plan of Koeberg Nuclear Power Station Unit 1.

The unit – which holds capacity of some 920MW – is on a planned maintenance outage in order to allow for the replacement of its steam generators.

This is in line with government’s Energy Action Plan Intervention One, which aims to ensure that all power stations are well maintained and working optimally to prevent further decline in the power utility’s energy availability.

The power utility explained that the first steam generator at the power station has been removed and placed in a storage building.

“This is a significant accomplishment for the Koeberg team, the contractor and the numerous local and international subcontractors involved in the project. It is a great relief to have reached this milestone as the steam generator replacement project has experienced numerous false starts in previous outages and some unexpected challenges during the execution in the current outage to get to this point in the project,” Eskom said on Tuesday.

The electricity company further explained that the removal of the steam generator is a precarious operation due to its size.

“The logistics of moving the steam generators from their installed [vertical] position out of containment (horizonal at an elevation of 20m), to placing them on a flatbed transporter (horizontal) can only be appreciated if one understands the size and weight of each steam generator.

“Each of them is 22m tall with a diameter of 4.5m (top half) and 3.5m (bottom half) and they each weigh over 320 tons. From here on all that is needed, is to take out the other two that are ready for lifting and install the three new steam generators,” Eskom said.

Several steps will still have to be taken before to ensure that the operation is executed. These include:

  • Rigging the remaining two steam generators out from their positions inside containment.
  • Rigging the three new steam generators into their exact position inside the containment building.
  • Performing the 6 critical welds (2 per steam generator) that joins the steam generators to the primary system piping.
  • Perform radiography on the welds to ensure they meet the code requirements.
  • Re-installing all the access platforms that enable people to work all the way up the steam generators (seven stories of permanent structures and temporary scaffolding).
  • Reinstall all the other piping connections (steam pipe at the top, feedwater pipe, and all the other smaller sampling and instrumentation connections) once access is available. In all cases performing the required level of quality control.
  • Install new thermal insulation over the whole steam generator surface and all the pipes that were worked on (around 120 tons was removed).
  • Remove all the temporary equipment that was required to be installed to allow the work to be done safely (scaffolding (85 tons), lead shielding (70 tons), electrical supplies (22 distribution boards and 1 km of cabling), etc).

Delay in return to service

Eskom said due to these steps having to be taken carefully, the return to service of the unit has been delayed.

“After [these steps], we still need to complete the maintenance activities scheduled for the outage, commission all the systems, refuel the reactor, and return the unit to service. Due to the delays that have already been experienced, the original return to service date for the unit is no longer achievable.

“Although every effort is being made to reduce the impact, we are currently running a few weeks late. The Generation production plan is being optimised to minimise as far as possible the impact of the projected delay on the system,” the power utility said.

 “In accordance with the safety analysis that was performed and submitted to the National Nuclear Regulator in support of the application to extend the plant life by 20 years, the steam generators are the last large component replacements that are needed to ensure Koeberg can operate safely for the requested additional period of operation.

“Thus, Eskom sees this milestone as an important step on the path to safely extending the life of Koeberg,” Eskom said.

Later this year, Koeberg’s second unit is expected to undergo a similar long outage to also replace its three steam generators. – SAnews.gov.za





Previous: Zulu honours social workers
Next: Emergency response required for climate change adaptation





Filed Under: South Africa Tagged With: SAnews

RSS Events

  • Hyde Park Corner Brings Out the Stars for This Year’s Spectacular Tree Lighting Celebration!
  • Step Inside: Prudential Center – Home of the New Jersey Devils
  • Exclusive November Imax Lineup Features Iconic Music Legend and a Hollywood Blockbuster
  • Kasi Republic Brings Kwaito, Kasi Cars and Ispantsula Style to Riversands Farm Village This Reconciliation Day
  • Festive Shopping Made Simple at Solly Kramer’s Parkhurst
  • LEDBox Hires Outdoor LED Screen Trailers with On-Site Crew
  • From Busking to the Business of Music: MEX Opens New Doors
  • P!NK Setlist: What to Expect From Her 2027 Live At Sphere Residency
  • Dinosaurs Stomp Into Cradlestone Mall This Festive Season
  • College Football Bowl Games Explained: What You Need to Know

About admin

The one with a "My Complex" - incurable but fun. Grumpy, Cynical, Wise and Idiotic. I can also be found HERE.

Footer

Latest News from Africa

  • Prince Albert – the New King of Jazz
  • Eritrea: Independence Cup in Southern Region
  • President El-Sisi Follows-up on the Evacuation of Egyptian Citizens from Sudan
  • United Arab Emirates welcomes initiation of talks between Sudanese Armed Forces and Rapid Support Forces
  • Ghana’s regions: why creating new territories has caused problems
  • Uganda Red Cross Delivers Relief Aid to Kisoro Floods-Affected Communities
  • President Ramaphosa alarmed over conflict, violence in eastern DRC
  • Mental health: almost half of Johannesburg students in new study screened positive for probable depression
  • Dietary Supplements for Dogs and Cats: Enhancing Well-being
  • Midwives scramble to ensure safe deliveries amid violence in Sudan

RSS MyPR’s Free Press Releases

  • Eksekuteurs vir Boedels en Testamente Shows How Retirement and a New Life Chapter Begin With One Conversation
  • Afri Air Publishes Farm Guides on DJI Dock 4 vs Dock 3 and Multi-Purpose Thermal Drones
  • Wings Appliance Repairs Shares Fridge Maintenance Guide to Help Midrand Households Avoid Breakdowns
  • Online Catalogue With Shelly Smart Automation Range and Bespoke 3D-Printed Installer Accessories
  • Lexpro Systems Shows Litigation Practices How to Bring Financial Clarity to Every Matter

© 2026 MyZA · Port Elizabeth, South Africa | Privacy Policy | MyZA content usage