Millions spent, six years gone, still no electricity for Eastern Cape villagers

13 October 2020 By admin

Photo of an electricity pole

A year after a construction company abandoned the site, villagers want to know when will they get electrification from a project that started in 2014. Photo: Nombulelo Damba-Hendrik

  • A mulit-million rand project to electrify villages near Mont Frere that started in 2014 ground to a halt in August 2019.
  • Only two of the seven designated villages have electricity.
  • The Mzimvubu Local Municipality promises to complete electrification by 15 December.

In 2014 a tender worth R31.2 million was awarded by the Mzimvubu Local Municipality in the Eastern Cape to electrify seven villages near Mount Frere.

The villages are Sivumela, Zigadini, Magontsini, Maxhegwini, Luyengweni, Lower Mnyamane and Chwebeni.

To date only two villages have electricity.

In the villages of Sivumela and Zigadini, electricity poles were set up four years ago and then left.

According to the villagers, by August 2019 the construction company had abandoned all its work sites.

But Mzimvubu Local Municipality spokesperson Nokhanyo Zembe said the construction company and RPS Ilangabi, a BEE consulting electrical engineering firm, had left the site without the consent of the municipality.

She said the reason remains unclear, but under the contract all payments went directly to RPS Ilangabi and the construction company was claiming RPS Ilangabi owed it R12 million. She said RPS Ilangabi was not answering the municipality’s calls.

Zembe said the contract ended in June 2019. The municipality had to date paid out R6.15 million since 2014, only for work it was satisfied with.

According to Zembe the total cost for the electrification of the 410 households in Zigadini and Sivumela is R8.2 million and an additional 37 households were being considered for another R740,000.

The municipality would not supply the details of the construction company.

Regis Masuku of RPS Ilangabi said, “We no longer have a contract with the municipality and I cannot comment on any allegations.”

Meanwhile villagers in Zigadini and Sivumela said they have lost hope of getting electricity. They also don’t have tap water. Instead they use a nearby river.

In the past year, the villagers have collected money and sent delegates to the municipality to get answers only to return with empty promises. Pat Jali, from Zigadini village, said, “Every month we are collecting R10 each house to send people to town to meet with municipality officials, but they are playing with us … They are not assisting us.

“This village is very old. We have old people who were born in 1938 here and they grew up here. Since 1994, people from this village have been voting but there’s no change.”

Ward committee member Bongeka Gcadinja said Sivumela was supposed to be the second location to have electricity and Zigadini the third location, but both were skipped by the construction company.

“The project went very slowly, because they will do one thing, like put up electric poles, then leave for months with no explanation,” she said.

Zembe said the appointment of a contractor is anticipated before 15 October 2020. Completion of work will take almost a month, as most of it has been done,” she said.

Zembe said the municipality promises Sivumela and Zigadini will be electrified before 15 December 2020.

© 2020 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

You may republish this article, so long as you credit the authors and GroundUp, and do not change the text. Please include a link back to the original article.

Source: GroundUp





Previous: Employees and customers left in the lurch by Swiss-owned STA Travel
Next: Nearly two million learners still not receiving meals at school





Filed Under: GroundUp Tagged With: GroundUp

RSS Events

  • Soweto Gets a New Summer Lifestyle Festival as Sugar People & Friends Celebrates Its First Birthday
  • Deftones Setlist: What to Expect From Their 2027 Live Show
  • Hyde Park Corner Brings Out the Stars for This Year’s Spectacular Tree Lighting Celebration!
  • Step Inside: Prudential Center – Home of the New Jersey Devils
  • Exclusive November Imax Lineup Features Iconic Music Legend and a Hollywood Blockbuster
  • Kasi Republic Brings Kwaito, Kasi Cars and Ispantsula Style to Riversands Farm Village This Reconciliation Day
  • Festive Shopping Made Simple at Solly Kramer’s Parkhurst
  • LEDBox Hires Outdoor LED Screen Trailers with On-Site Crew
  • From Busking to the Business of Music: MEX Opens New Doors
  • P!NK Setlist: What to Expect From Her 2027 Live At Sphere Residency

About admin

The one with a "My Complex" - incurable but fun. Grumpy, Cynical, Wise and Idiotic. I can also be found HERE.

Footer

Latest News from Africa

  • Prince Albert – the New King of Jazz
  • Eritrea: Independence Cup in Southern Region
  • President El-Sisi Follows-up on the Evacuation of Egyptian Citizens from Sudan
  • United Arab Emirates welcomes initiation of talks between Sudanese Armed Forces and Rapid Support Forces
  • Ghana’s regions: why creating new territories has caused problems
  • Uganda Red Cross Delivers Relief Aid to Kisoro Floods-Affected Communities
  • President Ramaphosa alarmed over conflict, violence in eastern DRC
  • Mental health: almost half of Johannesburg students in new study screened positive for probable depression
  • Dietary Supplements for Dogs and Cats: Enhancing Well-being
  • Midwives scramble to ensure safe deliveries amid violence in Sudan

RSS MyPR’s Free Press Releases

© 2026 MyZA · Port Elizabeth, South Africa | Privacy Policy | MyZA content usage