South Africa’s nuclear sector has failed its test: the Koeberg nuclear plant life extension

21 August 2022 By admin

South Africa’s only nuclear power plant, Koeberg, has frequently been in the news in 2022, all for the wrong reasons.

Its operating licence expires in 2024, and its continued operation thereafter depends on critical refurbishments and upgrades. Work on these finally began in January this year, but immediately ran into difficulties, forcing significant delays.

Koeberg is supplying only half of its power while work is in progress. This has amplified the crippling power shortages South Africa has been experiencing. This state of affairs, where the country effectively has 3% less generating power available than it would otherwise have, is expected to persist for the bulk of the next two years.

Other potential signs of turbulence linked to Koeberg include:

  • the delayed application to the nuclear regulator to extend the plant’s licence

  • the controversial dismissal of one of the regulator’s board members – an opponent of nuclear power – by the Minister of Mineral and Energy Resources

  • resignations of senior Koeberg staff, though there is no evidence that these were due to friction.

All of this has led to speculation that the Koeberg life extension exercise is in difficulty. In turn it casts doubt on the capacity of South Africa’s nuclear sector, and is likely to put to bed the highly ambitious proposals still advocated within the sector to build new nuclear plants.

Koeberg’s history

Koeberg, Africa’s only operational nuclear power station, 27km north of the Cape Town city centre, is reaching the end of its scheduled life cycle.

The plant consists of two units of just over 900 megawatts each, and together these contribute roughly 5% of South Africa’s electricity.

Koeberg was built by the French company Framatome between 1978 and 1984. In line with international practice, the plant was granted a 40-year operational licence which will expire in July 2024. Licensing the plant for a further 20 years is possible, as long as it meets specific safety criteria. Typically these involve particular upgrades and the replacement of various components.

So far the plant has operated reasonably safely, with only comparatively minor incidents recorded.

Some civil society groups have called for the closure of Koeberg when its current licence expires in 2024. South Africa’s extreme electricity crisis would make such a closure very difficult to absorb. While the construction of new nuclear plants is prohibitively expensive and very time intensive, extending the life span of an existing plant is in principle achievable in the short term and financially defensible.

The extension of the lifespan of Koeberg was also envisaged in the government endorsed 2019 Integrated Resource Plan for electricity.

Nuclear activities in South Africa are controlled by the National Nuclear Regulator. The regulator is expected to be guided by recommendations drawn up by experts commissioned by the International Atomic Energy Agency who inspected Koeberg in 2019. These recommendations include technical interventions for operating the plant safely for another 20 years. The most significant of these is the replacement of steam generators.

The upgrade is projected to cost R20 billion (US$1.2 billion). Most of this would go towards buying and installing six new steam generators.

The need to replace them was identified over 10 years ago, but protracted litigation over who would do the job held up the project. The operation was eventually scheduled for 2022.

Life extension project

The replacements and upgrades needed to secure a 20 year operating licence extension require each Koeberg unit to be shut down for a projected five months. Unit 2 was therefore switched off on 18 January 2022 and was supposed to reopen in June 2022. Unit 1 was then to go through the same process, starting in October.

Things then went wrong. The critical steam generator replacement was again postponed to 2023. The full reasons have not been officially disclosed. But there has been no denial of reports that the onsite storage facilities for the now radioactively contaminated old steam generators were not ready.

The delay in getting Koeberg Unit 2 up and running on schedule resulted in an additional 900 MW shortfall during South Africa’s most recent midwinter bout of severe power blackouts.

Unit 2 finally started operating again on 7 August, almost two months later than projected. Another outage of comparable duration is still required in 2023.

Significance for the nuclear sector

The mishandling of the Koeberg life extension project raises serious questions about the capacity of South Africa’s nuclear sector. This sector has advocated the building of a large fleet of new nuclear plants, implying that it could be done without major cost and time overruns. But the much smaller and far more straightforward Koeberg upgrade has not gone well.

South Africa should drop any ambitions for new nuclear plants. The nuclear sector should instead focus on its more modest target, namely to complete the Koeberg upgrade, run the plant for another 20 years and then complete the potentially problematic decommissioning.

Source: The Conversation





Previous: Ambassador of Thailand chaired the 261st Association of Southeast Asian Nations (ASEAN) Committee in Cairo (ACC) Meeting
Next: Recent United Nations Mission in South Sudan (UNMISS) peace concert in Aweil draws massive participation and useful debate





Filed Under: Africa Tagged With: mypr

RSS Events

  • Soweto Gets a New Summer Lifestyle Festival as Sugar People & Friends Celebrates Its First Birthday
  • Deftones Setlist: What to Expect From Their 2027 Live Show
  • Hyde Park Corner Brings Out the Stars for This Year’s Spectacular Tree Lighting Celebration!
  • Step Inside: Prudential Center – Home of the New Jersey Devils
  • Exclusive November Imax Lineup Features Iconic Music Legend and a Hollywood Blockbuster
  • Kasi Republic Brings Kwaito, Kasi Cars and Ispantsula Style to Riversands Farm Village This Reconciliation Day
  • Festive Shopping Made Simple at Solly Kramer’s Parkhurst
  • LEDBox Hires Outdoor LED Screen Trailers with On-Site Crew
  • From Busking to the Business of Music: MEX Opens New Doors
  • P!NK Setlist: What to Expect From Her 2027 Live At Sphere Residency

About admin

The one with a "My Complex" - incurable but fun. Grumpy, Cynical, Wise and Idiotic. I can also be found HERE.

Footer

Latest News from Africa

  • Prince Albert – the New King of Jazz
  • Eritrea: Independence Cup in Southern Region
  • President El-Sisi Follows-up on the Evacuation of Egyptian Citizens from Sudan
  • United Arab Emirates welcomes initiation of talks between Sudanese Armed Forces and Rapid Support Forces
  • Ghana’s regions: why creating new territories has caused problems
  • Uganda Red Cross Delivers Relief Aid to Kisoro Floods-Affected Communities
  • President Ramaphosa alarmed over conflict, violence in eastern DRC
  • Mental health: almost half of Johannesburg students in new study screened positive for probable depression
  • Dietary Supplements for Dogs and Cats: Enhancing Well-being
  • Midwives scramble to ensure safe deliveries amid violence in Sudan

RSS MyPR’s Free Press Releases

  • One Billion, Four Hundred and Fifty-Five Million, Seven Hundred and Ninety-Six Thousand, Eight Hundred and Forty-Six Times
  • Anchor Entrepreneur Awards announces 2026 finalists
  • Aremimo to Mark Fifth Anniversary With Grand Event in Addis Ababa on 5 December
  • Which Is Better: Petrol or Battery? That’s the Wrong Question
  • Two More Reasons for Brahman Hills to Celebrate!

© 2026 MyZA · Port Elizabeth, South Africa | Privacy Policy | MyZA content usage